T-1013 Project North Park Overpass Project

Various resources are made available here to inform about the Northpark Drive Overpass Project. Included are downloadable files as well as videos, all of which are publicly available via participating entities.

Project Documents

CONSTRUCTION SCHEDULE

Northpark 3 WK look ahead 04.23.26

Please see the attached look ahead schedule for the Northpark Dr. Overpass Project T-1013 with the following updates to the construction schedule:

The dirt crew will continue the excavation and grading of north and south detention ponds for the next three weeks then install cement stabilization, after final grade, then install pond liner.

Crews will continue subgrade work on the east header of the bridge, then cement treat subgrade, and place base and bondbreaker, completion anticipated in +/- 2 weeks.

The structures crew will begin forming the bridge abutment cap, concrete to poured next week.

The structures crew will then proceed with forming and pouring the bridge abutment backwall. Then continue work on the retaining walls, after topping out walls, will install coping.

Concrete work will continue on UPRR ROW with focus on of installation of multi-use pathway, completion anticipated in 1 week.

The paving crew will begin forming EB Northpark in front of Dunkin Donuts. The first pour will be on Wednesday; the second pour will be the following week. After the bondbreaker is placed at the east bridge header, the paving crew will begin preparing and pouring the paving up to the beginning of the bridge.

The sidewalk crew will be working on the curb ramp and sidewalks East of Anderson Road to Marco’s Pizza, then move to NAPA Auto and install sidewalks eastward to Russel Palmer.  After will install permanent driveway at the Mermaid Car Wash.

The signal crew will continue installing permanent signals at intersection of Russel Plamer in preparation for walkthrough with the City of Houston Public Works Department.  After confirmation with Public Works, the final configuration at that intersection will be activated.

The street light crew will also continue installation of street light foundations and light poles throughout.

Ditch 1 reestablishment has been completed and will be hydro-mulched with grass seed week of 5/4.

Please Note – Work will continue in the center median of Northpark Dr in preparation to put traffic in its final configuration. There are and will be many obstructions and potential hazards in this area, including construction workers and vehicles.

The traveling public is restricted from crossing into the work zone and is only allowed to turn around at the delineated cross over areas. 

 

Video Resources

Northpark Drive Traffic Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Design Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Overpass Project

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Additional Resources

PUBLIC MEETING DOCUMENTS