Various resources are made available here to inform about the Northpark Drive Overpass Project. Included are downloadable files as well as videos, all of which are publicly available via participating entities.
Project Documents
CONSTRUCTION SCHEDULE
Northpark 3 WK look ahead 06.12.2025
Please see the attached look ahead schedule for Northpark with the following updates:
The bore machine crew is currently on hold due to conflicts with both bore alignments. This week, a CenterPoint electric pole was removed from the southern bore alignment and work should resume on the southern bore early next week.
A revised work plan has been submitted for approval by UPRR for a conflict at the northern bore alignment; consisting of the discovery of an abandoned water line located within UPRR ROW, and previously unknown to UPRR. Operations will be on hold pending approval of a revised work plan, consisting of the removal of the section of the water line that is in direct conflict with the southern bore alignment. Once the work plan is approved by UPRR, the bore operation will continue and should last approximately more two weeks. This bore operation requires 24-hour work being performed under the observation of RailPros and UPRR until both bores are completed.
The storm sewer crew will continue work on JB 16 installation on the SW corner of LP 494 and Northpark. Once complete, they will excavate in the vicinity of Sonic and construct a cast-in-place drainage structure and tie-in the parking lot drainage to the main trunkline outfall. They will then move to Whataburger and set the last junction box for the EB drainage which includes tie-in for the movie theater parking lot. Storm sewer laterals and manholes will be placed on WB Northpark from PNC Bank to I-69.
Drainage work along NB LP 494 is still on hold pending Centerpoint Gas conflict resolution.
Cement treated base will be placed on NB LP 494 this coming Monday and Tuesday, followed up by asphalt bondbreaker this coming Friday or the following Monday depending on the weather. The dirt crew will begin cutting subgrade material in the median from Culvers to I-69 In preparation for Fast Track Concrete to be placed after the storm sewer laterals are placed.
The paving crew will continue operations on WB Northpark from Kolache Factory to Public Storage. Then they will move to the WB Northpark in front of PNC Bank to start pouring Fast Track Paving westwards to I-69.
Demolition of the Existing WB lanes from Culver’s to I-69 will continue and should be finished up this coming week.
Russel Palmer intersection paving is scheduled for the weekend of 6/27.
The sidewalk and electrical subcontractors will continue working on their respective items of work along EB Northpark from Italiano’s to the east end of the project in preparation to switch traffic on the new lanes of Northpark two weeks after the 4th of July holiday.
VIDEO & PHOTOS
Video Resources
Northpark Drive Traffic Simulation
YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video
Northpark Drive Design Simulation
YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video
Northpark Drive Overpass Project
YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video
Additional Resources
PUBLIC MEETING DOCUMENTS
- Project Email List
- Meeting Handouts
- Public Meeting Photos
- Public Comment Forms