T-1013 Project North Park Overpass Project

Various resources are made available here to inform about the Northpark Drive Overpass Project. Included are downloadable files as well as videos, all of which are publicly available via participating entities.

Project Documents

CONSTRUCTION SCHEDULE

Northpark 3 WK look ahead 04.24.2025

Please see the attached look ahead schedule for Northpark with the following updates:

The large storm sewer crew will be completing the 7×6 RCB’s on EB Northpark in front of the Dry Cleaners and installing Junction boxes JB-06 and JB-16; and tie in Sonic Drive-In into the existing 7×6 trunkline. They will then move to the east side of the UPRR tracks to complete the 4×4 run of RCB now that the PS Lightwave utility conflict has been resolved. This same crew will excavate the bore pit shaft in front of the Extra Space Storage starting the week of May 5th for the bore subcontractor to begin work tentatively the last week of May for the dual 60″ bores under the UPRR tracks.

The waterline crew will be working in coordination with Mickie Services and MUD 98 to make the fireline switch over to the new 8″ waterline Monday through Wednesday next week, with the installation of the TS&V on Tuesday April 29th. Once this switch is made, the existing 8″ MUD 98 line can be abandoned.

The small storm sewer crew will continue placing laterals and drainage structures along the NB LP 494 lanes both north and south of Northpark working in unison with the private utility companies that are still currently in this same area.

Next week the dirt crew will continue working on the future EB lanes of Northpark from I-69 to LP 494 and begin demolishing the parking lots from the Exxon gas station up to the Sonic Drive-In in preparation to begin the subgrade work for the future EB Northpark at that location.

The paving crews will continue their work on the EB Northpark paving from Italiano’s eastward to the end of the project.  Fast-track paving will be used for the remaining driveway block outs. Fast track paving is scheduled to be poured on Tuesday April 29th in front of the PNC Bank which will complete the WB Northpark from LP 494 to the Chick- Fil-A, in preparation for the switch traffic at that location.

Video Resources

Northpark Drive Traffic Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Design Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Overpass Project

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Additional Resources

PUBLIC MEETING DOCUMENTS