T-1013 Project North Park Overpass Project

Various resources are made available here to inform about the Northpark Drive Overpass Project. Included are downloadable files as well as videos, all of which are publicly available via participating entities.

Project Documents

CONSTRUCTION SCHEDULE

Northpark 3 WK look ahead 09.04.2025

Please see the attached look ahead schedule for Northpark with the following updates:

Preparatory activities related to the underground bore work within the UPRR ROW are ongoing after a temporary pause related to 2 conflicts.  Mobilization by bore subcontractors on the project will occur the beginning week of 8/8/25, once the 2 conflicts are removed, all bore activities are scheduled to be completed within two weeks.

The storm sewer crew will work on the WB Northpark east of the 494 installing inlets in preparation for a future traffic switch. They will then move to the south side of Northpark from I-69 to the Whataburger, to place drainage. A second storm sewer crew will continue to place the drainage pipe and structures on the WB lanes of Northpark. Once the traffic switch occurs on 9/11/25 the crew will move to complete the remainder of the storm sewer system from Anderson Road to Italiano’s.

The dirt crew will continue working on the subgrade of the WB Northpark, grading temp driveways, and placing cement to stabilize the subgrade in preparation to place cement treated base in these areas. They will begin working on grading and placing temporary detours in preparation for the traffic switch scheduled for 8/10/25. 

After the traffic Switch, they will begin work on EB Northpark from Marco’s pizza to Italiano’s.  Grading operations will begin in the middle of September on both the north and south detention ponds. Excavation of the retaining wall level pad will begin after the WB traffic switch occurs.

For the next three weeks, the paving crew will be working concurrently on both the WB Northpark in the center median from PNC Bank to I-69 pouring fast track paving and on EB Northpark from Anderson Road to King’s mill to tie in concrete paving previously placed.

The asphalt subcontractor is scheduled for the week of 9/22/25 to be onsite to place bond breaker on both EB and WB Northpark in preparation to place concrete paving.

The sidewalk and driveways will continue working on the project behind the paving crews.

The Illumination Subcontractor has been put on hold pending approval of streetlight foundation design changes by Houston Public Works Department.

Video Resources

Northpark Drive Traffic Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Design Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Overpass Project

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Additional Resources

PUBLIC MEETING DOCUMENTS