T-1013 Project North Park Overpass Project

Various resources are made available here to inform about the Northpark Drive Overpass Project. Included are downloadable files as well as videos, all of which are publicly available via participating entities.

Project Documents

CONSTRUCTION SCHEDULE

Northpark 3 WK look ahead 10.16.2025

Please see the attached look ahead schedule for the Northpark Dr. Overpass Project T-1013 with the following updates to the construction schedule:

Work on the northern bore alignment has been completed. Crews will be mobilizing off the job, and site cleanup will be done by HBC crews.

The storm sewer crew will continue setting drainage structures and RCP EB Northpark Between I-69 and LP 494 to complete the laterals in this area including the 60″ equalizer pipe between the North and South Ponds. Work then will begin by setting the RCB drainage structures up to the bores underneath the railroad. Subcontractor will begin working on the two cast in place junction boxes on either side of the railroad to tie in the drainage to the outfalls. The first week of November 7×6 RCB lateral across Northpark will be installed in phases under single lane closures during the daytime hours to complete the last drainage tie in to the drainage outfall ditches.

The dirt crew will be working on preparing the subgrade in preparation to cement treat and place base from east of Italiano’s back to Marco’s pizza. Once completed they will move in front of Dunkin’ Donuts to begin working on the subgrade and begin excavation for the retaining wall leveling pad. Additionally, subgrade preparation will be done from I-69 to Whataburger where concrete paving was just removed.

The concrete paving crews will continue paving WB Northpark from Millennium Motors to the project end this coming week as well as beginning the preparation for the 15″ fast track paving from I-69 to Whataburger.

Currently, King’s Mill Phase 1 paving preparation and pour is scheduled to take place the week of 10/27/2025 being poured on 10/31/2025. Once completed, traffic will be switched over to the new pavement, and work will begin on Phase 2 paving of King’s Mill.

The asphalt subcontractor is scheduled to be on site November 3rd and 4th to place the asphalt bondbreaker on the EB lanes of Northpark from Marco’s Pizza to Italiano’s

The electrical subcontractor will be on site to work on the permanent pedestrian signals at I-69 and Northpark Dr. Once completed, they will begin their boring operation to install the conduit for the ITS fiber optic system on the northside of Northpark from I-69 to PNC Bank.

Video Resources

Northpark Drive Traffic Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Design Simulation

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Northpark Drive Overpass Project

YouTube video, will play in place. To enlarge choose the full screen icon in the lower right of the video

Additional Resources

PUBLIC MEETING DOCUMENTS